Austral Gold Provides Update on Casposo Plant Refurbishment
Austral Gold (OTCQB: AGLDF) reported significant progress in the refurbishment of its 100% owned Casposo Plant in Argentina. The company is targeting plant commissioning for August 2025, with commercial operations expected to begin in the second half of 2025.
Key completed activities include primary crusher refurbishment, SAG engine repair, and modifications to piping and ducts. Ongoing work includes SAG mill relining, installation of new hydrocyclones, and filter band refurbishment. The company has already hired 55 employees and plans to increase the workforce to 116 employees by August.
Austral Gold is preparing to commence toll processing in November 2025 under an agreement with Challenger Gold, while an independent consultant advances a technical report compliant with NI 43-101 and JORC 2012 standards to evaluate processing Casposo's own mineralized material.
Austral Gold (OTCQB: AGLDF) ha segnalato notevoli progressi nella ristrutturazione del suo impianto Casposo di proprietà al 100% in Argentina. L'azienda prevede di avviare la messa in funzione dell'impianto entro agosto 2025, con l'inizio delle operazioni commerciali previsto nella seconda metà del 2025.
Le attività principali già completate includono la ristrutturazione del frantoio primario, la riparazione del motore SAG e modifiche alle tubazioni e ai condotti. I lavori in corso comprendono la rivestitura del mulino SAG, l'installazione di nuovi idrocicloni e la ristrutturazione della fascia del filtro. L'azienda ha già assunto 55 dipendenti e prevede di aumentare il personale a 116 dipendenti entro agosto.
Austral Gold si sta preparando ad avviare il processo di lavorazione a pedaggio a partire da novembre 2025 in base a un accordo con Challenger Gold, mentre un consulente indipendente sta elaborando un rapporto tecnico conforme agli standard NI 43-101 e JORC 2012 per valutare il trattamento del materiale mineralizzato di proprietà di Casposo.
Austral Gold (OTCQB: AGLDF) informó avances significativos en la renovación de su Planta Casposo, de propiedad 100%, en Argentina. La compañía tiene como objetivo la puesta en marcha de la planta para agosto de 2025, con operaciones comerciales previstas para la segunda mitad de 2025.
Las actividades clave finalizadas incluyen la renovación del triturador primario, reparación del motor SAG y modificaciones en tuberías y conductos. Los trabajos en curso incluyen el revestimiento del molino SAG, la instalación de nuevos hidrociclones y la renovación de la banda del filtro. La empresa ya ha contratado a 55 empleados y planea aumentar la plantilla a 116 empleados para agosto.
Austral Gold se está preparando para comenzar el procesamiento por peaje en noviembre de 2025 bajo un acuerdo con Challenger Gold, mientras un consultor independiente avanza en un informe técnico conforme a las normas NI 43-101 y JORC 2012 para evaluar el procesamiento del material mineralizado propio de Casposo.
Austral Gold (OTCQB: AGLDF)� 아르헨티나에 위치� 100% 소유� Casposo 공장� 개보� 작업에서 상당� 진전� 보고했습니다. 회사� 2025� 8�� 공장 가동을 목표� 하고 있으�, 상업 운영은 2025� 하반기에 시작� 예정입니�.
완료� 주요 작업으로� 1� 파쇄� 개보�, SAG 엔진 수리, 배관 � 덕트 수정� 포함됩니�. 진행 중인 작업에는 SAG 밀 라이�, 새로� 하이드로사이클론 설치, 필터 밴드 개보수가 있습니다. 회사� 이미 55명의 직원� 고용했으� 8월까지 116�으로 인력� 늘릴 계획입니�.
Austral Gold� Challenger Gold와� 계약� 따라 2025� 11�� � 가공을 시작� 준비를 하고 있으�, 독립 컨설턴트가 NI 43-101 � JORC 2012 기준� 부합하� 기술 보고서를 진행하여 Casposo 자체 광물 자재 가� 평가� 진행 중입니다.
Austral Gold (OTCQB : AGLDF) a annoncé des progrès significatifs dans la rénovation de son site Casposo, détenu à 100%, en Argentine. La société vise la mise en service de l'usine pour août 2025, avec un début des opérations commerciales prévu pour le second semestre 2025.
Les principales activités achevées comprennent la rénovation du concasseur primaire, la réparation du moteur SAG et des modifications des tuyauteries et conduits. Les travaux en cours incluent le rechargement de la meule SAG, l'installation de nouveaux hydrocyclones et la rénovation de la bande du filtre. La société a déjà recruté 55 employés et prévoit d'augmenter son effectif à 116 employés d'ici août.
Austral Gold se prépare à commencer le traitement à façon en novembre 2025 dans le cadre d'un accord avec Challenger Gold, tandis qu'un consultant indépendant avance un rapport technique conforme aux normes NI 43-101 et JORC 2012 pour évaluer le traitement du matériel minéralisé propre à Casposo.
Austral Gold (OTCQB: AGLDF) meldete bedeutende Fortschritte bei der Sanierung seiner 100%igen Casposo-Anlage in Argentinien. Das Unternehmen plant die Inbetriebnahme der Anlage für August 2025, wobei der kommerzielle Betrieb in der zweiten Hälfte des Jahres 2025 beginnen soll.
Wichtige abgeschlossene Arbeiten umfassen die Überholung des Primärbrechers, die Reparatur des SAG-Motors sowie Änderungen an Rohrleitungen und Kanälen. Laufende Arbeiten beinhalten das Neubeschichten der SAG-Mühle, die Installation neuer Hydrozyklone und die Überholung des Filterbands. Das Unternehmen hat bereits 55 Mitarbeiter eingestellt und plant, die Belegschaft bis August auf 116 Mitarbeiter zu erhöhen.
Austral Gold bereitet sich darauf vor, im Rahmen einer Vereinbarung mit Challenger Gold im November 2025 mit der Lohnverarbeitung zu beginnen, während ein unabhängiger Berater einen technischen Bericht nach NI 43-101 und JORC 2012 Standards erstellt, um die Verarbeitung des eigenen mineralisierten Materials von Casposo zu bewerten.
- Plant refurbishment is on schedule for August 2025 commissioning
- Several key components already completed including primary crusher and SAG engine repair
- Workforce expansion from 55 to 116 employees demonstrates operational readiness
- Local community engagement through training programs for plant operators
- Toll processing agreement with Challenger Gold secured for November 2025
- Some critical components still pending completion including SAG mill relining and hydrocyclone installation
- Technical report for processing own mineralized material still under development
Casposo Plant refurbishment steadily advancing and nearing completion
Commissioning targeted for August 2025
Commercial operations on track to commence during second half of 2025
Sydney, Australia--(Newsfile Corp. - July 29, 2025) - Austral Gold Limited (ASX: AGD) (TSXV: AGLD) (OTCQB: AGLDF) ("Austral" or the "Company"), an established gold producer, is pleased to provide an update on the refurbishment of its
Austral Gold's Chief Executive Officer, Stabro Kasaneva, said: "We are pleased with the progress on the refurbishment of the Casposo Plant in Argentina, with commissioning targeted for August 2025. In parallel, our independent consultant continues to advance a technical report prepared that complies with NI 43-101 and JORC 2012 standards to assess the feasibility of processing Casposo's own mineralised material. We remain on track to commence toll processing in November 2025 under the Toll Processing Agreement ("the Agreement") with ASX-listed Challenger Gold."
Refurbishment Plant Overview
Most of the key activities scheduled for Q2 2025 have been completed, with the remainder underway and expected to be finalised in the first half of August, ahead of commissioning.
Status of Q2 2025 planned activities:
- Primary crusher refurbishment: Completed (Figure 1).
- SAG mill relining: Underway; expected to be completed with recently arrived materials.
- SAG engine repair: Completed (Figure 2).
- Installation of new hydrocyclones: Underway; awaiting vendor's committed delivery date.
- Engines and reducers for leaching tanks and CCD's repair: Completed (Figure 3).
- Filter band refurbishment: Underway; all purchased materials received.
- Modifications and improvement of piping and ducts: Completed.
Figure 1: Primary Crusher (Area 100). The Primary Crusher has been completed and is ready for operation. Installation of a sampling tower is currently underway in this area to improve grade control of the material to be sourced from the Hualilán Project.
To view an enhanced version of this graphic, please visit:
Figure 2: SAG Mill (Area 200). The SAG mill engine, part of the Grinding Circuit, has been repaired, and the inching system was successfully tested.
To view an enhanced version of this graphic, please visit:
Figure 3: Leaching Tanks (Area 300). The engines and reducers for the leaching tanks and CCDs have been repaired.
To view an enhanced version of this graphic, please visit:
Main works planned before Commissioning:
Finalise SAG mill relining and complete its full installation.
Complete Installation of new hydrocyclones.
Finalise Filter band refurbishment.
Complete testing of the Plant's electrical circuits.
In addition, the Company is progressing well with its recruitment efforts, with 55 employees currently on board. During August, the workforce is expected to increase by approximately 61 employees, bringing the total headcount to 116. As part of its commitment to local engagement, the Company delivered a targeted three-day training program in the Calingasta Village, aimed at identifying potential candidates and supporting the development of a skilled local workforce for plant operator roles.
Figure 4: Training Course in Calingasta Village to recruit local plant operators.
To view an enhanced version of this graphic, please visit:
About Austral Gold
Austral Gold is a growing gold and silver mining producer building a portfolio of quality assets in the Americas based on three strategic pillars: production, exploration and equity investments. Austral continues to lay the foundation for its growth strategy by advancing its attractive portfolio of producing and exploration assets.
For more information, please visit the Company's website at
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
Release approved by the Company's Chief Executive Officer of Austral Gold, Stabro Kasaneva.
For additional information, please contact:
David Hwang | Jose Bordogna |
Joint Company Secretary | Chief Financial Officer and Joint Company Secretary |
Austral Gold Limited | Austral Gold Limited |
[email protected] | [email protected] |
+61 433 292 290 | +61 466 892 307 |
Forward-Looking Statements
Statements in this announcement that are not historical facts are forward-looking statements. Forward-looking statements are statements that are not historical, and consist primarily of projections - statements regarding future plans, expectations and developments. Words such as "expects", "intends", "plans", "may", "could", "potential", "should", "anticipates", "likely", "believes" and words of similar import tend to identify forward-looking statements. Forward-looking statements in this announcement include statements regarding our expectations for the refurbishment of the Casposo Plant in Argentina, our independent consultant continues to advance a technical report prepared that complies with NI 43-101 and JORC 2012 standards to assess the feasibility of processing Casposo's own mineralised material, the projected increase of approximately 61 employees at Casposo during August 2025, and our expectation that we can continue to lay the foundation for our growth strategy by advancing our attractive portfolio of producing and exploration assets.
All of these forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ from those expressed or implied, including, without limitation, uncertainty of exploration programs, development plans and cost estimates, commodity price fluctuations; political or economic instability and regulatory changes; currency fluctuations, the state of the capital markets, uncertainty in the measurement of mineral resources and reserves and other risks and hazards related to the exploration of a mineral property, and the availability of capital and a skilled workforce. You are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. Austral cannot assure you that actual events, performance or results will be consistent with these forward-looking statements, and management's assumptions may prove to be incorrect. Austral's forward-looking statements reflect current expectations regarding future events and operating performance and speak only as of the date hereof and Austral does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. For the reasons set forth above, you should not place undue reliance on forward-looking statements.
To view the source version of this press release, please visit